A permit lists a daily maximum and a monthly average for the same pollutant. One daily result is above the monthly average but below the daily maximum. What should the lead operator conclude?
Answer: B. The daily result meets the daily maximum; review all required results to determine whether the monthly average is met.
A monthly average is based on the required results for the month, while a daily maximum applies to the daily value defined by the permit. For example, one result can be above the monthly limit number without causing a monthly-average violation if the completed monthly average meets that limit. A applies the monthly average to one day, C skips the monthly calculation, and D substitutes a weekly result that the permit did not require.
A permitted outfall had no discharge during the full reporting period. How should the operator complete the DMR for that outfall?
Answer: C. Record the DMR no-discharge entry for the outfall and period, and retain records that support why no sample was collected.
A no-discharge entry reports that no effluent left that outfall; it is different from a measured zero or a result below detection. For example, a seasonal outfall that stayed closed should have supporting gate, flow, or operating records. A invents measured zeros, B leaves an unexplained blank and checks unrelated totals, and D reports laboratory findings from a sample that did not exist.
During a storm, operators intentionally route primary effluent around the secondary process and discharge it through the permitted outfall. In a separate event, wastewater spills from a collection-system manhole. Which classification is correct?
Answer: A. The routed primary effluent is a bypass; the manhole spill is an overflow.
A bypass is an intentional diversion around part of a treatment facility, while an overflow is wastewater released from the collection system before reaching normal treatment. For example, opening a treatment-unit bypass gate is different from sewage leaving a surcharged manhole. B reverses the terms, and C and D treat two different events as one type even though each still requires its applicable reporting response.
An industrial discharge is followed by two findings: a pollutant passes through the plant and causes an effluent permit violation, and the biological process is upset enough to disrupt treatment. How should the lead operator describe the findings?
Answer: B. The permit violation shows pass through, while the disrupted biological process shows interference.
Pass through is a discharge that leaves the POTW and causes or contributes to a permit violation; interference disrupts the POTW, its processes, or compliant sludge use or disposal. For example, a metal can pass through into effluent while a toxic load interferes with the biological process. A reverses the terms, while C and D use one label for two different effects.
The DMR shows a weekly average of 21.0 mg/L against a weekly average limit of 20.0 mg/L. The monthly average and every daily maximum are within their own limits. How should the lead operator classify the weekly result?
Answer: C. Report a weekly average violation because the reported weekly value exceeds its weekly limit.
Each permit limit stands on its own, so a weekly average of 21.0 mg/L violates a weekly average limit of 20.0 mg/L. It is like meeting a speed limit on several roads but exceeding the limit on another road. A and B apply the wrong averaging periods, while D changes the type of limit that was exceeded.